Audit opinion worsens
The Free State Department of Human Settlements has recorded a deterioration in its latest audit outcome, receiving a qualified opinion from the Auditor-General for the 2025/26 financial year. The result is a step down from the unqualified opinion with findings received previously and has renewed scrutiny of the department’s financial controls, procurement processes and ability to deliver housing projects.
The findings, as cited by the Democratic Alliance in the Free State Provincial Legislature, point to weaknesses that extend beyond accounting records. They include insufficient supporting evidence for transfers and subsidies paid to households, incorrect provisions and payables linked to contractor retentions, and the failure to disclose fruitless and wasteful expenditure associated with breaches of the VAT Act.
A qualified audit opinion does not mean that every transaction or programme is invalid. It indicates that the Auditor-General found material issues in parts of the department’s financial reporting or supporting evidence. For residents waiting for housing, however, the significance is practical: weaknesses in controls can affect whether projects are completed on time, whether public money is properly accounted for and whether beneficiaries receive the services planned for them.
Housing target falls short
The department had planned to complete 1 663 housing units during the year. According to the audit findings reported by the DA, only 696 units were completed, representing 42% of the target. The shortfall leaves a substantial gap between the department’s stated programme and the number of homes delivered.
| Measure | Reported figure |
|---|---|
| Housing units planned | 1 663 |
| Units completed | 696 |
| Delivery against target | 42% |
| Irregular expenditure | R53 million |
| Claims against the department | R899 million |
| Average creditor payment period | 311 days |
The gap has consequences for families who remain without adequate housing and related services. The DA said the figures reflected households still waiting for suitable accommodation, sanitation and dependable services. The source report also recorded infrastructure problems in the department’s programmes, adding to concerns about whether projects are being properly planned, monitored and maintained.
Financial pressure and unpaid creditors
The audit findings include R53 million in irregular expenditure. The department also faces claims totalling R899 million, while creditors reportedly wait an average of 311 days for payment. Such delays can place pressure on contractors and suppliers working on public projects, although the available findings do not state how each claim arose or how many businesses are affected.
These figures also make the department’s procurement and contract-management practices a central issue. The audit found that contractor retentions were recorded as provisions or payables even though the contractors were not entitled to those amounts. It further found that fruitless and wasteful expenditure linked to contraventions of the VAT Act had not been disclosed. These are control failures that require clear explanations and corrective action from the department.
Dark & Silver City under scrutiny
The Dark & Silver City project illustrates the risks associated with weak oversight. Work was delayed by extensions and variations that had not been approved. The project incurred an overspend of R16 million, while R15 million in professional fees was claimed outside the National Housing Code.
The redevelopment was planned to provide 812 community residential units. By August 2026, only 130 units had been completed and 19 were occupied. The figures show the difference between the scale of the planned intervention and the limited number of units available to residents at that point.
The department’s MEC, Saki Mokoena, has described the first phased beneficiary occupations as part of turnaround efforts implemented after 2024. That explanation will now be measured against the latest audit findings, the pace of construction and the department’s ability to prevent further delays and unapproved project changes.
Hawks investigating three projects
The Directorate for Priority Crime Investigation, known as the Hawks, is investigating three Free State housing projects, including Dark & Silver City. The available information does not indicate whether charges have been brought or provide a finding from the investigation. The investigation should therefore not be treated as proof of wrongdoing by any individual or contractor.
For the provincial department, the immediate accountability questions are clear:
- Why did housing delivery reach only 42% of the annual target?
- How will the department address the reported irregular expenditure and the long delay in paying creditors?
- What controls will prevent unapproved extensions, variations and claims outside the National Housing Code?
- How will beneficiaries be informed about revised completion and occupation timelines?
The audit outcome places renewed responsibility on the department to strengthen its financial systems and provide transparent updates on stalled or delayed projects. For people waiting for homes, the issue is not only whether money was spent, but whether spending produced completed units, functioning services and lawful, properly managed projects.
“Behind these figures are families left without adequate housing, sanitation and reliable services.”
The qualified opinion, missed delivery target and project-level concerns now require a formal response from the department and sustained oversight by the Free State Legislature. Until those issues are addressed, residents will continue to carry the consequences of delays in a programme intended to provide secure housing and basic services.