Construction has started on a new Tesla Supercharger station in Repentigny, with eight charging stalls planned near Autoroute 40. The site is being developed in the parking area behind Benny&Co. on Boulevard Louis-Philippe-Picard, placing the project close to one of the city's main transportation corridors.
The Repentigny installation is at an early stage. Underground conduit has been laid and forms have been put in place for the concrete footings, according to information shared by Supercharger tracker MarcoRP on Nov. 11. The source did not provide a projected opening date, and the station is not yet operational.
Two Quebec projects, different technology
The Repentigny project is expected to use eight V3 charging stalls. It is being built at the same time as another eight-stall Tesla station in neighbouring Terrebonne, but the two developments will not use the same generation of equipment.
| Location | Planned stalls | Equipment | Construction status |
|---|---|---|---|
| Repentigny | 8 | V3 | Underground conduit and footing forms in place |
| Terrebonne | 8 | V4 posts and V4 power supply units | Posts and equipment installed; site fenced |
The Terrebonne station is being installed at an A&W on Chemin Gascon. It is expected to be Quebec's first true V4 Supercharger, because it will use both V4 charging posts and V4 power supply unit hardware. The equipment is capable of charging at up to 500 kilowatts, according to the report.
That configuration differs from V3.5 installations that use V4 posts with V3 cabinets. Those systems have a maximum charging speed of 325 kilowatts. Photos of the Terrebonne project show the charging posts and equipment already installed, although the location remains fenced off while work continues.
Part of a broader Quebec expansion
The two projects come as Tesla continues adding sites to its Quebec Supercharger network. Recent additions include stations in Gatineau, Drummondville and Mont-Tremblant. The Gatineau station, which has eight V4 charging posts, had its equipment installed in November 2025 but waited nearly a year before being activated. It opened earlier this month, according to the source material.
Drummondville's station opened in August, while the Mont-Tremblant location came online in September. The Mont-Tremblant site added 24 stalls on Sept. 29 and included a commemorative charger marking Tesla's 3,000th Canadian Supercharger.
We've finally got V4 Superchargers coming to Quebec!!!
That observation, posted by MarcoRP while documenting the Terrebonne work, underscores the technical distinction between the neighbouring projects. For Repentigny, the immediate development is a separate eight-stall V3 installation. Its location near the A-40 will make the site part of the charging network serving the city and motorists travelling through the area once construction is completed and the station is activated. No opening schedule has been announced.
- Repentigny: eight V3 stalls planned behind Benny&Co. on Boulevard Louis-Philippe-Picard.
- Terrebonne: eight full V4 stalls under construction at the A&W on Chemin Gascon.
- Quebec network: recent openings have included Gatineau, Drummondville and Mont-Tremblant.