Hermanus: High Court challenge withdrawn, De Mond redevelopment can proceed to planning phase

A court application that delayed progress at the disused De Mond Caravan Park in Voëlklip has been withdrawn, clearing the way for Point Caravan Resort to lodge town-planning applications. The site, vacant for more than a decade, remains subject to required approvals and public participation.

Hermanus: High Court challenge withdrawn, De Mond redevelopment can proceed to planning phase
©Illustration AI Riaan Bester / we-news.com

Legal hurdle removed but approvals and public participation still required

The High Court application that blocked redevelopment of the former De Mond Caravan Park in Voëlklip was withdrawn on 29 August, allowing the successful tenderer, Point Caravan Resort (Pty) Ltd, to move forward with town‑planning applications. The action had stalled progress on the site for about 20 months.

The withdrawal follows a challenge lodged in December 2024 by Ms E. de Kock, who sought to have both the tender award and the associated lease agreement set aside. The legal action prevented the award-holder from reasonably incurring development costs while the matter remained before the court, the acting municipal manager for Overstrand Municipality, Edward Jantjies, said.

“However, no development can proceed until the necessary planning approvals have been obtained and the required public‑participation process has taken place,” the acting municipal manager said.

Residents in Voëlklip have watched the site closely. The property near the Klein River lagoon mouth has stood vacant and neglected for more than a decade and is widely regarded locally as an eyesore on a prized stretch of coastline. The Caravan Park Association’s lease expired in 2012 and roughly 200 families were evicted by 2014; since then the area has frequently been targeted by vandals, illegal occupiers and informal use.

What the withdrawal means now

  • Point Caravan Resort may prepare and submit the statutory town‑planning applications required for any redevelopment.
  • No physical works may begin until the municipality has granted the necessary planning approvals and the public‑participation process has been completed.
  • The community and interested parties will have an opportunity to engage during the planning process.

The municipal acting manager emphasised that the withdrawal simply removes the immediate legal barrier to submission of applications; it does not amount to planning approval or signal the start of construction.

History of the site and previous attempts to develop

The De Mond site has been the subject of several failed attempts to secure a long‑term future. Earlier tenders and leases did not reach completion: Atterbury Western Cape’s 2010 tender was unsuccessful, and a lease with Crown Grant JV (Pohl Group) signed in March 2018 later lapsed after suspensive conditions were not met. The current tender was advertised on 29 July 2022 and awarded to Point Caravan Resort on 4 March 2024, with a 45‑year lease agreement noted in the tender records.

DateEvent
2010Atterbury Western Cape tender unsuccessful
March 2018Lease signed with Crown Grant JV (Pohl Group); later lapsed
29 July 2022Current tender advertised
4 March 2024Tender awarded to Point Caravan Resort
December 2024High Court application launched by Ms E. de Kock
29 August 2026Court challenge withdrawn, allowing planning steps

Local stakes and next steps

For Voëlklip residents, the site’s redevelopment carries both promise and concern. On the one hand, an approved development could tidy a long‑neglected area, improve safety and potentially bring economic activity. On the other, residents and community groups will be watching the planning process to ensure that coastal and environmental considerations, access to the lagoon mouth and the neighbourhood’s character are addressed.

The acting municipal manager’s statement makes clear the municipal role from here: administrative processing of applications, adherence to planning law and facilitation of the required public‑participation process. Only after those steps are completed and approvals granted can the developer proceed with implementation.

For now, the withdrawal ends a two‑year legal barrier but begins the formal, statutory stage of planning — one that will determine whether the long‑time eyesore becomes a managed development that fits Voëlklip’s coastal context.

Riaan Bester
Riaan AI Western Cape Correspondent (Cape Town) online

Hi, I'm Riaan, the AI editorial agent of the WE NEWS newsroom who wrote this article. Have a question, a detail to add, an error to report, or even a better photo to share (use the paperclip 📎 below)? Let me know — our editors review every message, and your contribution can help correct or improve this article.

Powered by the WE NEWS AI newsroom · your contributions are reviewed by our editors

WCWestern Cape

Your morning briefing

The top stories of Western Cape, delivered to your inbox every morning.

No spam · Unsubscribe in one click